Evans Creek Energy Storage (ERCOT-26INR0260) — Project Summary

Queue ID
ERCOT-26INR0260
Capacity
102.96 MW
Technology
Battery
Status
active
Location
Val Verde, TX
Region
ERCOT
Developer
Evans Creek Energy Storage LLC
IA Status
Facility Study

Evans Creek Energy Storage

ERCOT-26INR0260BetaActiveBatteryERCOTLBNL + Live

102.96 MW storage in Val Verde, TX · In queue since October 2023 · Proposed COD April 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

102.96 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Facilities Study50%
Queue EntryOct 25, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

Queue history
26INR0260 · 36 monthly ERCOT reports, Oct 2023 – Sep 2026

Projected COD moved

1 time

Jun 2026 → Apr 2028

Net change

+22 months

first report to latest

Capacity

103 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 25, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Apr 1, 2028
From queue filing
Developer in saved assessment
Doral Renewables
Filed as Evans Creek Energy Storage LLC
Status at research time
Active
Active — in Facility Study phase per ERCOT queue, no construction announcements yet
Financing
Not recorded

Milestones in this assessment

IA executedOct 2023Latest in this assessment

Project entered ERCOT queue in Facility Study phase

doral-llc.com
Research sources and reasoning (3 recorded sources)

medium confidence at research time

  1. doral-llc.com/projects/evans-creek-energy-storage/
  2. doral-llc.com/solution/battery-storage/
  3. interconnection.fyi/project/ercot-26inr0260

Commercial operation date: Only LBNL queue data provides a COD target of April 2028. No news sources or press releases mention specific operational timelines for Evans Creek Energy Storage.

Developer: LBNL filing uses project-LLC 'Evans Creek Energy Storage LLC'. Doral LLC website lists Evans Creek Energy Storage as one of their projects, confirming Doral Renewables as the parent operating company.

Status: LBNL status shows 'active' in Facility Study phase. No news coverage indicates construction start or permitting milestones for this specific project.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Evans Creek Energy Storage is a proposed 102.96 MW battery storage project in Val Verde County, Texas. Developed by Evans Creek Energy Storage LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-26INR0260. The project entered the queue on October 25, 2023, with a proposed commercial operation date of April 1, 2028. Its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing Evans Creek Energy Storage Project operating plant (EIA ID 68334). It has also been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Val Verde

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Evans Creek Energy Storage LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Comstock 138kV Substation (PSSE Bus #8683)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
HIGH
POI Substation
Comstock Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-19

View all articles