Evans Creek Energy Storage is a 103 MW Battery project in Texas, currently active.
Evans Creek Energy Storage is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-04-01.
- Queue ID
- ERCOT-26INR0260
- Location
- Val Verde, Texas
- Technology
- Battery
- Developer
- Evans Creek Energy Storage
- Market / region
- ERCOT
- Point of interconnection
- Comstock 138kV Substation (PSSE Bus #8683)
What stands out
Evans Creek Energy Storage is a 103 MW Battery project in Texas with status active.
Evans Creek Energy Storage is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2028-04-01.
Latest linked story: “ContourGlobal’s First Renewable Energy Facility in U.S. Comes Online in Colorado” (Business Wire, 2025-09-04).
Market and operating context
- Queue date
- 2023-10-25
- Proposed COD
- 2028-04-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.