Cottontail Energy Center
200.85 MW storage in Colorado, TX · In queue since October 2023 · Proposed COD October 2027
200.85 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4 years
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-19
Projected COD moved
1 time
Mar 2026 → Oct 2027
Net change
+19 months
first report to latest
Capacity
201 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Tax abatement application filed with Colorado County Commissioners Court
co.colorado.tx.usResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- infrasure.ai/project/ercot-26inr0259-cottontail-energy-center
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- co.colorado.tx.us/upload/page/9816/Minutes%202025/CCM%20-%20June%209%202025.pdf
- interconnection.fyi/project/ercot-26inr0259
Commercial operation date: LBNL queue filing shows October 19, 2027 COD. No independent news sources provide alternative dates; third-party aggregators (Cleanview, InfraSure, interconnection.fyi) simply mirror the LBNL filing.
Developer: LBNL filing uses project-LLC 'Cottontail Energy Center, LLC'. InfraSure and AWS buildout pipeline identify the actual developer as 'Mission Clean Energy LLC', the operating parent company.
Status: LBNL shows 'Active' status at Facility Study stage. Colorado County Commissioners Court minutes from June 9, 2025 confirm active local permitting activity with tax abatement application from Cottontail Energy Center, LLC.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Cottontail Energy Center is a proposed 200.85 MW battery storage project located in Colorado County, Texas. The project, developed by Mission Clean Energy LLC, is interconnected within the ERCOT region under queue ID ERCOT-26INR0259. It entered the interconnection queue on October 25, 2023, and has a proposed commercial operation date of October 19, 2027. The project's interconnection status is currently in the Facility Study phase.
The Cottontail Energy Center development has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Colorado
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cottontail Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7258 Glidden Substation 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Glidden Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Cottontail Energy Center
Data-driven briefing on Cottontail Energy Center — fleet, generation, financial, and news signals.
Energy Center
Data-driven briefing on Energy Center — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.