Operation Sunshine
603.2 MW hybrid in Concho, TX · In queue since November 2023 · Proposed COD April 2029
603.2 MW
Capacity
1
Components
Solar
3 years
In Queue
IA Executed
IA Phase
Signed Aug 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 9m
IA → COD
3y 8m
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2029-04-01
Projected COD moved
3 times
Jul 2026 → Apr 2029
Net change
+33 months
first report to latest
Capacity
602 → 603 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed for the 603 MW Operation Sunshine solar+battery project (LBNL date; Infrasure confirms an Aug 2025 signing).
infrasure.aiResearch sources and reasoning (3 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-26inr0255-operation-sunshine
- cleanview.co/planned-solar-projects/TX/26INR0255/operation-sunshine
- cleanview.co/power-projects/planned/solar-farms/texas/26INR0255/operation-sunshine
Commercial operation date: Infrasure lists 'Proposed COD: 2028-03-12' for ERCOT-26INR0255, and Cleanview says 'expected to come online in March 2028'. Both are about a year earlier than the LBNL date of 2029-04-01. Both are queue aggregators, probably drawing on the same ERCOT data, and a second Cleanview page still says 2029, so this is weak evidence.
Developer: LBNL and Infrasure both name Duck Creek Solar, LLC, a project-level entity, and no source identifies a parent or operating company. The news-extracted facts (Ørsted, Energy Capital Partners, Helena Energy Center, 518 MW, online) describe a different project and were discarded.
Status: LBNL reports an active status with IA Executed (2025-08-27), and Infrasure confirms an IA signed in Aug 2025. The Infrasure page also says 'Facility Study phase', which conflicts with that and was not used. No source shows construction or operation.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Operation Sunshine is a proposed 602.1 MW solar generation project located in Concho County, Texas. The project, developed by Duck Creek Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0255, with a queue entry date of November 14, 2023. The proposed commercial operation date is March 12, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 602.1 MW of solar generation capacity. Operation Sunshine has been the subject of recent news coverage, with three articles categorized as industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Concho
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Duck Creek Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7077 Amos Creek 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.