Santa Monica Solar (ERCOT-26INR0228) — Project Summary

Queue ID
ERCOT-26INR0228
Capacity
105.85 MW
Technology
Solar
Status
active
Location
Navarro, TX
Region
ERCOT
Developer
Karol Solar IV
IA Status
Facility Study

Santa Monica Solar

ERCOT-26INR0228BetaActiveSolarERCOTLBNL + Live

105.85 MW generation in Navarro, TX · In queue since September 2023 · Proposed COD September 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

105.85 MW

Capacity

1

Components

Solar

3y 2m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5 years

Facilities Study50%
Queue EntrySep 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-20

Queue history
26INR0228 · 24 monthly ERCOT reports, Oct 2024 – Sep 2026

Projected COD moved

1 time

Sep 2027 → Sep 2028

Net change

+12 months

first report to latest

Capacity

106 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 7, 2023
Facilities study approvedAug 12, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 10y 1m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneround-the-clock dispatchable solar energyPOWER Magazine · 2016-10-12

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Sep 20, 2028
From queue filing
Developer in saved assessment
Karol Solar IV
From queue filing
Status at research time
Active
Active — Facility Study stage per LBNL queue, no public construction or financing announcements found
Financing
Not recorded

Milestones in this assessment

IA executedSep 2023Latest in this assessment

Entered ERCOT queue in Facility Study stage

cleanview.co
Research sources and reasoning (1 recorded sources)

low confidence at research time

  1. cleanview.co/planned-solar-projects/TX/26INR0228/santa-monica-solar

Commercial operation date: Only LBNL queue data provides a COD estimate (September 2028). Cleanview aggregator confirms this date but appears to source from LBNL. No independent press releases or developer announcements found to validate or update this target.

Developer: Only LBNL filing identifies 'Karol Solar IV' as developer. No press releases, corporate announcements, or news coverage found for this entity or project. Unable to determine if this is a shell LLC or operating company name.

Status: LBNL reports 'active' status in Facility Study phase as of queue date September 2023. No subsequent news coverage or milestones identified to update this status.

Project lifecycle
as of 2016-10-12
PhaseOnlinePOWER Magazine · 2016-10-12
OperationalYesPOWER Magazine · 2016-10-12
TechnologySolarPOWER Magazine · 2016-10-12
COD achievedReportedPOWER Magazine · 2016-10-12

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Santa Monica Solar project is a proposed 105.85 MW solar generation facility in Navarro County, Texas. The project, developed by Karol Solar IV, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0228, with a queue entry date of September 7, 2023. The proposed commercial operation date is September 20, 2028, and the interconnection agreement status is currently in the Facility Study phase.

The Santa Monica Solar project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Navarro

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Karol Solar IV

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Navarro Switching Station

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.