Rock Rose BESS
211.5 MW storage in Fort Bend, TX · In queue since September 2023 · Proposed COD March 2027
211.5 MW
Capacity
1
Components
Battery
3y 2m
In Queue
IA Executed
IA Phase
Signed Jun 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
9 months
IA → COD
2y 9m
Total Duration
9 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-03-19
Projected COD moved
2 times
Jul 2026 → Mar 2027
Net change
+8 months
first report to latest
Capacity
209 → 209 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
- 2025-10·Advanced Power→Greenflash Infrastructureprnewswire.com
Milestones in this assessment
Greenflash acquired 200 MW/400 MWh Rock Rose project from Advanced Power
businesswire.comGreenflash secured 10+ GWh portfolio financing including Rock Rose for data center power delivery
businesswire.comResearch sources and reasoning (8 recorded sources)
high confidence at research time
- prnewswire.com/news-releases/advanced-power-closes-sale-of-rock-rose-energy-storage-302579957.html
- businesswire.com/news/home/20251014822795/en/Greenflash-Acquires-200-MW-400-MWh-Pre-NTP-Battery-Storage-Project-in-Texas
- mercomcapital.com/greenflash-acquires-200-mw-400-mwh-battery-storage-project-in-texas/
- rigzone.com/news/greenflash_acquires_planned_200_mw_bess_project_in_texas-15-oct-2025-182083-article/
- renewablesnow.com/news/greenflash-snatches-up-200-mw-battery-project-in-texas-1283254/
- businesswire.com/news/home/20260106334587/en/Greenflash-Secures-10-GWh-of-Battery-Storage-Capacity-to-Accelerate-Data-Center-Power-Delivery
- idcnova.com/html/1/59/153/4858.html
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0201/rock-rose-bess
Commercial operation date: LBNL proposed COD is 2027-03-19. Multiple sources (idcnova.com, Cleanview) confirm mid-2027 target post-acquisition by Greenflash in Oct 2025, representing a slight refinement but no major disagreement.
Developer: LBNL filing entity is Rock Rose Energy Storage LLC (shell). Advanced Power developed the project and sold it to Greenflash Infrastructure in October 2025, confirmed by PR Newswire, Business Wire, and multiple trade publications.
Status: LBNL status is Active with IA Executed (June 2024). Greenflash acquisition announcement describes project as 'pre-NTP' indicating development stage prior to construction start.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Rock Rose Energy BESS project is a proposed 211.5 MW battery storage project located in Fort Bend County, Texas. Developed by Rock Rose Energy Storage LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-26INR0201. The project entered the interconnection queue on September 22, 2023, and has a proposed commercial operation date of March 19, 2027.
The interconnection agreement for the Rock Rose Energy BESS project was executed on June 15, 2024. The point of interconnection is the 44070 Whaley 345 kV substation. The project has been mentioned in recent news coverage related to deals.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fort Bend
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rock Rose Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44070 Whaley 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- JAY_RN_1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Rock Rose BESS
Data-driven briefing on Rock Rose BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.