Briefing/projectactive
Rock Rose BESS is a 212 MW Battery project in Texas, currently active.
Rock Rose Energy Storage is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-03-19.
- Queue ID
- ERCOT-26INR0201
- Location
- Fort Bend, Texas
- Technology
- Battery
- Developer
- Rock Rose Energy Storage
- Market / region
- ERCOT
- Point of interconnection
- 44070 Whaley 345 kV
What stands out
1
Rock Rose BESS is a 212 MW Battery project in Texas with status active.
2
Rock Rose Energy Storage is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-03-19.
Market and operating context
- Queue date
- 2023-09-22
- Proposed COD
- 2027-03-19
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.