Realitos Solar SLF (ERCOT-26INR0196) — Project Summary

Queue ID
ERCOT-26INR0196
Capacity
150.49 MW
Technology
Solar+Battery
Status
suspended
Location
Duval, TX
Region
ERCOT
Developer
Mesquite Creek LLC
IA Status
Facility Study

Realitos Solar SLF

ERCOT-26INR0196BetaSuspendedSolarBatteryERCOTLBNL + Live

150.49 MW hybrid in Duval, TX · In queue since September 2023 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

150.49 MW

Capacity

1

Components

Solar

3y 2m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 3m

Suspended50%
Queue EntrySep 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-15

Queue history
26INR0196 · 37 monthly ERCOT reports, Aug 2023 – Aug 2026

Projected COD moved

1 time

Dec 2026 → Dec 2028

Net change

+24 months

first report to latest

Capacity

151 → 150 MW

changed in the reports

Latest stage

Screening started

last listed Aug 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 7, 2023
On ERCOT's inactive listSep 2026 – Sep 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 15, 2028
From queue filing
Developer in saved assessment
Redeux Energy
Filed as Mesquite Creek LLC
Status at research time
Active
Active — Facility Study stage, no IA executed yet. Early-stage development with 5% build-chance per ercotqueue.com analysis.
Financing
Not recorded

Milestones in this assessment

IA executedLatest in this assessment

Facility Study in progress per LBNL; no IA executed yet

eta-publications.lbl.gov
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
  2. cleanview.co/power-projects/developers/redeux-energy
  3. cleanview.co/developer/redeux-energy
  4. ercotqueue.com/project/26INR0196
  5. ercotqueue.com/developer/mesquite-creek-llc

Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-12-15. No independent news sources or press releases found to validate or contradict this date; all search results merely echo the LBNL filing data.

Developer: LBNL filing entity is 'Mesquite Creek LLC' (project shell). Cleanview aggregator pages list this project under 'Redeux Energy's Projects and Development Pipeline', indicating Redeux Energy is the operating parent company behind the Mesquite Creek LLC filing entity.

Status: LBNL status is 'active' with IA status 'Facility Study'. No news of withdrawal, construction start, or financing. All aggregator sources confirm 'Planned' or 'Active' status with no IA.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Realitos Solar SLF (queue ID ERCOT-26INR0196) is a proposed solar-plus-battery hybrid project in Duval County, Texas, developed by Mesquite Creek LLC. The project has a total capacity of 150.49 MW, all of it attributed to the solar component. A battery storage component is also listed, but no separate capacity figure has been provided for it. The project would connect to the grid at the Bruni (#8297) – Crestonio (#8695) 138 kV line, operated by AEP.

The project entered the Electric Reliability Council of Texas (ERCOT) interconnection queue on September 7, 2023. Its proposed commercial operation date is December 15, 2028. The project's interconnection agreement process is at the Facility Study stage. Its current queue status is listed as suspended.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Aug 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Duval

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Mesquite Creek LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Bruni (#8297) – Crestonio (#8695) 138 kV line; AEP

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.