Realitos Solar SLF
Type
Entity Briefing
Entity
Realitos Solar SLF
Generated
2026-10-19T06:11:21.033Z

Briefing on Realitos Solar SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
150 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-12-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Realitos Solar SLF is a 150 MW Solar+Battery project in Texas, currently active.

Mesquite Creek LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-15.

Queue ID
ERCOT-26INR0196
Location
Duval, Texas
Technology
Solar+Battery
Developer
Mesquite Creek LLC
Market / region
ERCOT
Point of interconnection
Bruni (#8297) – Crestonio (#8695) 138 kV line; AEP

What stands out

1

Realitos Solar SLF is a 150 MW Solar+Battery project in Texas with status active.

2

Mesquite Creek LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-12-15.

Market and operating context

Queue date
2023-09-07
Proposed COD
2028-12-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Realitos Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0196
LocationDuval, Texas
TechnologySolar+Battery
DeveloperMesquite Creek LLC
Market / regionERCOT
Point of interconnectionBruni (#8297) – Crestonio (#8695) 138 kV line; AEP
Queue date2023-09-07
Proposed COD2028-12-15