Skipjack Energy Storage
150.6 MW storage in Brazoria, TX · In queue since July 2023 · Proposed COD February 2028
150.6 MW
Capacity
1
Components
Battery
3y 4m
In Queue
IA Executed
IA Phase
Signed Aug 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 1m
IA → COD
3y 6m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-02-28
Projected COD moved
2 times
Aug 2026 → Feb 2028
Net change
+18 months
first report to latest
Capacity
151 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT transmission providers
interchange.puc.texas.govERCOT November 2024 capacity chart lists 2027 commercial operation target
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- ercot.com/files/docs/2024/12/06/Capacity%20Changes%20by%20Fuel%20Type%20Charts_November_2024.xlsx
- cleanview.co/power-projects/developers/esvolta
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercotqueue.com/developer/skipper-energy-storage-llc
Commercial operation date: ERCOT's November 2024 capacity chart lists Skipjack with a 2027 COD, one year earlier than LBNL's 2028-02-28 filing date. This reflects a more current developer target.
Developer: LBNL filing uses project-LLC 'Skipper Energy Storage LLC'. Cleanview's esVolta pipeline page lists Skipjack Energy Storage as a 151 MW battery project in esVolta's development portfolio, indicating esVolta is the operating parent company.
Status: LBNL shows IA executed 2024-08-13. Texas PUC filings from September-October 2024 confirm ongoing interconnection documentation between CenterPoint/Oncor and Skipper Energy Storage LLC. ERCOT queue tracker notes FIS pending.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Skipjack Energy Storage is a proposed 150.6 MW battery storage project located in Brazoria County, Texas. The developer is Skipper Energy Storage LLC. The project is in the ERCOT interconnection queue as entry ERCOT-26INR0189, with a queue entry date of July 31, 2023, and a proposed commercial operation date of February 28, 2028. The interconnection agreement (IA) has been executed as of August 13, 2024.
The proposed project consists of 150.6 MW of battery storage capacity. Skipjack Energy Storage has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Skipper Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 42980 Nash - 44010 W A Parish ckt #2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.