Arc Energy Storage (ERCOT-26INR0184) — Project Summary

Queue ID
ERCOT-26INR0184
Capacity
204.5 MW
Technology
Battery
Status
active
Location
Lamar, TX
Region
ERCOT
Developer
Paris Energy Storage, LLC
IA Status
Facility Study

Arc Energy Storage

ERCOT-26INR0184BetaActiveBatteryERCOTLBNL + Live

204.5 MW storage in Lamar, TX · In queue since July 2023 · Proposed COD June 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

204.5 MW

Capacity

1

Components

Battery

3y 4m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 11m

Facilities Study50%
Queue EntryJul 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

Queue history
26INR0184 · 39 monthly ERCOT reports, Jul 2023 – Sep 2026

Projected COD moved

5 times

Dec 2026 → Jun 2028

Net change

+18 months

first report to latest

Capacity

206 → 205 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 31, 2023
Facilities study approvedMay 2, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneCOD achievedTeslaNorth.com · 2025-10-18

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jun 2028
From queue filing
Developer in saved assessment
Paris Energy Storage, LLC
From queue filing
Status at research time
Active
Active in ERCOT queue at Facility Study stage — no public evidence of construction activity, financing, or permitting progress
Financing
Not recorded

Milestones in this assessment

IA executedJul 2023Latest in this assessment

Entered ERCOT interconnection queue at Facility Study stage

cleanview.co
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0184/arc-energy-storage
  2. renewablesinfo.org/project/ercot-26inr0184-arc-energy-storage
  3. infrasure.ai/project/ercot-26inr0184-arc-energy-storage

Commercial operation date: LBNL queue filing shows June 2028 COD. Third-party aggregators (Cleanview, renewablesinfo.org) echo this date but provide no independent verification. No press releases, financing announcements, or developer statements found to validate or update the timeline.

Developer: Only source is LBNL filing naming 'Paris Energy Storage, LLC'. No corporate website, press releases, parent company identification, or news coverage found. Unable to determine if this is a shell LLC or operating entity.

Status: LBNL shows 'active' status at Facility Study phase (pre-IA execution). No news coverage, groundbreaking announcements, or financing signals found to indicate project advancement beyond queue position.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Arc Energy Storage project is a proposed 204.5 MW battery storage project located in Lamar County, Texas. Developed by Paris Energy Storage, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-26INR0184. It entered the interconnection queue on July 31, 2023, with a proposed commercial operation date of April 18, 2028. The project's interconnection status is currently in the Facility Study phase.

The Arc Energy Storage project has been featured in recent news coverage related to the energy industry, grid infrastructure, and business deals.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Lamar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Paris Energy Storage, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 1693 Paris Switch - 11806 ENLOE T8

Data Source

LBNL + Live

DeveloperAmeresco, Inc.TeslaNorth.com · 2025-10-18
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.