Arc Energy Storage
204.5 MW storage in Lamar, TX · In queue since July 2023 · Proposed COD June 2028
204.5 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Projected COD moved
5 times
Dec 2026 → Jun 2028
Net change
+18 months
first report to latest
Capacity
206 → 205 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue at Facility Study stage
cleanview.coResearch sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0184/arc-energy-storage
- renewablesinfo.org/project/ercot-26inr0184-arc-energy-storage
- infrasure.ai/project/ercot-26inr0184-arc-energy-storage
Commercial operation date: LBNL queue filing shows June 2028 COD. Third-party aggregators (Cleanview, renewablesinfo.org) echo this date but provide no independent verification. No press releases, financing announcements, or developer statements found to validate or update the timeline.
Developer: Only source is LBNL filing naming 'Paris Energy Storage, LLC'. No corporate website, press releases, parent company identification, or news coverage found. Unable to determine if this is a shell LLC or operating entity.
Status: LBNL shows 'active' status at Facility Study phase (pre-IA execution). No news coverage, groundbreaking announcements, or financing signals found to indicate project advancement beyond queue position.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Arc Energy Storage project is a proposed 204.5 MW battery storage project located in Lamar County, Texas. Developed by Paris Energy Storage, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-26INR0184. It entered the interconnection queue on July 31, 2023, with a proposed commercial operation date of April 18, 2028. The project's interconnection status is currently in the Facility Study phase.
The Arc Energy Storage project has been featured in recent news coverage related to the energy industry, grid infrastructure, and business deals.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Paris Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 1693 Paris Switch - 11806 ENLOE T8
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesArc Energy Storage
Data-driven briefing on Arc Energy Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Paris (KY)
Data-driven briefing on Paris — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.