Wittig Solar (ERCOT-26INR0144) — Project Summary

Queue ID
ERCOT-26INR0144
Capacity
106.9 MW
Technology
Solar
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
Greenalia Solar Power Wittig LLC
IA Status
Facility Study

Wittig Solar

ERCOT-26INR0144BetaActiveSolarERCOTLBNL + Live

106.9 MW generation in Wharton, TX · In queue since February 2024 · Proposed COD October 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

106.9 MW

Capacity

1

Components

Solar

2y 9m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 8m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-30

Queue history
26INR0144 · 32 monthly ERCOT reports, Feb 2024 – Sep 2026

Projected COD moved

1 time

Sep 2027 → Oct 2028

Net change

+13 months

first report to latest

Capacity

107 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2028
From queue filing
Developer in saved assessment
Greenalia
Filed as Greenalia Solar Power Wittig LLC
Status at research time
Active
Active — Facility Study stage, no IA executed. Early-stage development with no construction or financing announcements.
Financing
Not recorded

Milestones in this assessment

IA executedFeb 2024Latest in this assessment

Entered ERCOT queue at Facility Study stage

ercotqueue.com
Research sources and reasoning (6 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/solar-farms/texas/67568_WIGSP/wittig-solar-park
  2. aterio.io/insights/us-energy-projects/ep/wittig-solar-park-project
  3. interconnection.fyi/project/ercot-26inr0144
  4. cleanview.co/power-projects/planned/solar-farms/texas/26INR0144/wittig-solar
  5. ercotqueue.com/project/26INR0144
  6. ercotqueue.com/developer/greenalia-solar-power-wittig-llc

Commercial operation date: LBNL shows 2028-10-30. Cleanview aggregators show conflicting dates: one says 2028, another 2029, one 2027. No authoritative press release or financing announcement exists. LBNL date is most reliable given lack of developer-sourced updates.

Developer: LBNL filing entity is 'Greenalia Solar Power Wittig LLC' — a project-specific shell. Parent company is Greenalia, a Spanish renewable energy developer. No ownership changes detected in search results.

Status: LBNL shows 'active' status at Facility Study stage. No news of permitting, financing, or construction. Third-party trackers (ercotqueue.com) assign 5% build-chance, indicating speculative early-stage project.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Wittig Solar project is a proposed solar generation facility with a total capacity of 106.9 MW, located in Wharton County, Texas. The developer is Greenalia Solar Power Wittig LLC. This project is interconnected within the ERCOT region and is listed in the ERCOT interconnection queue as entry ERCOT-26INR0144, with a queue entry date of February 27, 2024. The proposed commercial operation date is October 30, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The proposed project is linked to the existing Wittig Solar Park operating plant (EIA ID 67568). Recent news coverage has discussed this development project.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wharton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Greenalia Solar Power Wittig LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

138 kV Gulftie (#43340) – San Bernard (#43110)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
SAN_SANMIGG1
POI Substation
Texas Gulf Sulfur Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.