Pioneer Hutt Solar (Alternative POI)
116 MW generation in Midland, TX · In queue since June 2023 · Proposed COD July 2028
116 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Projected COD moved
1 time
Dec 2026 → Jul 2028
Net change
+19 months
first report to latest
Capacity
116 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Prior proposed completion date before change to July 2028
interconnectionfyi.substack.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-26inr0121
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-ad5
- ercotqueue.com/developer/nextera
Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-07-01. One Interconnection.fyi update from April 2025 mentions a prior target of December 2026 that was changed, but no current alternative date is provided in search results. Defaulting to LBNL filing date.
Developer: LBNL filing entity is 'NextEra Energy Interconnection Holdings LLC', a project-specific interconnection vehicle. Search results (ercotqueue.com) confirm this is one of 5 filing-entity LLCs aggregated under parent 'NextEra Energy', the operating company.
Status: LBNL reports 'active' status with 'Facility Study' interconnection phase. No search results indicate withdrawal, construction start, or operational status. Status remains as filed.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Pioneer Hutt Solar (Alternative POI) project is a proposed 116 MW solar generation facility in Midland County, Texas. The project, being developed by NextEra Energy Interconnection Holdings LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0121, with a queue entry date of June 28, 2023.
The proposed commercial operation date for the Pioneer Hutt Solar (Alternative POI) project is July 1, 2028. Its interconnection status is currently in the Facility Study phase, and the Point of Interconnection (POI) is the TAP 345kV 11028 Odessa Ehv - 59901 Grelton (West C) substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Midland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NextEra Energy Interconnection Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345kV 11028 Odessa Ehv - 59901 Grelton (West C)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OECCS_1
- POI Substation
- Odessa EHV Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
A specific company (e.g., NextEra Energy, Duke Energy)
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra Energy
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra entity test
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra-Blackwell Wind, LLC
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.