Freedom Falcon BESS
501.9 MW storage in Zapata, TX · In queue since June 2023 · Proposed COD August 2028
501.9 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-11
Projected COD moved
1 time
May 2026 → Aug 2028
Net change
+27 months
first report to latest
Capacity
502 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-26inr0107
- newsletter.interconnection.fyi/p/interconnection-weekly-project-updates-ad5
- ercotqueue.com/project/26INR0107
- infrasure.ai/project/ercot-26inr0107-freedom-falcon-bess
- groundtrace.io/developers/falcon-bess-llc-33azklk3s37yi
Commercial operation date: Only queue-derived sources (LBNL, ERCOT GIS mirrors such as infrasure and cleanview) give a COD of August 2028. The April 2025 newsletter notes the date slipped from 2026-05-30 to 2028-08-10, but no developer press release or financing-backed target exists to contradict or confirm it.
Developer: LBNL, ercotqueue.com, infrasure and groundtrace all name Falcon BESS, LLC as developer. No parent or operating company is identified in any source, so the LLC is used as is.
Status: LBNL, interconnection.fyi and ercotqueue.com all show the project as active with no IA, and groundtrace says it is queued and not under construction. The interXdata 'operational' label conflicts with all of these and with LBNL's is_operational=false, so it is treated as a normalization error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Freedom Falcon BESS project is a proposed 501.9 MW battery storage project located in Zapata County, Texas. Developed by Falcon BESS, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0107, with a queue entry date of June 28, 2023. The proposed commercial operation date is August 11, 2028.
The project's interconnection status is currently in the Facility Study phase. The Point of Interconnection (POI) is Tap 345kV 80307 Delsol - 80225 Cenizo CKT#2. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Zapata
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Falcon BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV #80224 Tiempo - #80227 Rapido
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.