HyFuels Green Lake Solar
347 MW generation in Victoria, TX · In queue since September 2022 · Proposed COD December 2027
347 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Projected COD moved
1 time
Oct 2026 → Dec 2027
Net change
+14 months
first report to latest
Capacity
121 → 347 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-26inr0019
- infrasure.ai/project/ercot-26inr0019-hyfuels-green-lake-solar
- ercotqueue.com/project/26INR0019
- app.nrgmap.com/queues/ercot-26inr0019
- ercotqueue.com/developer/hyfuels-green-lake-solar-llc
Commercial operation date: Every source that gives a COD (interconnection.fyi, infrasure.ai) repeats the ERCOT queue's proposed completion date of December 1, 2027. No developer press release or news item gives an independent, financing-backed date.
Developer: All sources name only the filing LLC, and none identifies a parent or operating company. The power-eng.com snippet about a 1+ GW portfolio with an adjacent green ammonia project may be related, but it does not name this project or a buyer, so no ownership change is asserted.
Status: ERCOT-derived trackers (NRG Map, interconnection.fyi, ercotqueue.com) all show the project as active with no IA. One aggregator (interxdata) labels it 'operational', which contradicts the IA status and the LBNL snapshot, so I treated it as a data error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The HyFuels Green Lake Solar project is a proposed 346 MW solar generation project located in Victoria County, Texas. The developer is HyFuels Green Lake Solar LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0019, with a queue entry date of September 27, 2022. The proposed commercial operation date is December 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 8189 Tungsten 138kV location. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
HyFuels Green Lake Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Dokmai 138kV Substation (bus #80090)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Substation 41
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.