Beck_Road BESS1
9.99 MW storage in Bexar, TX · In queue since July 2025 · Proposed COD January 2026
9.99 MW
Capacity
1
Components
Battery
1y 4m
In Queue
IA Executed
IA Phase
Signed Aug 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 month
IA → COD
5 months
Total Duration
1 month
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-01-01
Projected COD moved
3 times
Jan 2026 → Mar 2026
Net change
+2 months
first report to latest
Capacity
10 MW
unchanged in the reports
Latest stage
Commercial operation
last listed Apr 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Beck_Road BESS1 is a proposed battery energy storage development project located in Bexar County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by Bexar Corrilla LLC, the project has a total planned capacity of 9.99 MW, consisting entirely of a single battery storage component. The project is designated in the ERCOT interconnection queue under the identifier ERCOT-25INR0717 and currently holds an active status.
The project entered the ERCOT interconnection queue on July 11, 2025, and executed its interconnection agreement (IA) on August 12, 2025. Its proposed commercial operation date is January 1, 2026. The planned point of interconnection is the Beck Road transmission service provider station (station code Z0), connecting at the 138 kV transmission level via load transformer LXFMR3 at PTI bus number 5035.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Apr 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bexar Corrilla LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TSP Station Name: Beck Road TSP Station Code: Z0 Load Name / Load Transformer Name: LXFMR3 Bus #: PTI Bus Number: 5035 Voltage (Transmission level kV): 138 Node (associated w/ load/load XFMR in NMMS): 0001
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.