Query
Beck_Road BESS1
Type
Entity Briefing
Entity
Beck_Road BESS1
State
TN
Technology
battery
Generated
2026-10-19T16:13:14.356Z

Briefing on Beck_Road BESS1

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
10 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-01-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Beck_Road BESS1 is a 10 MW Battery project in Texas, currently active.

Bexar Corrilla LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-01-01.

Queue ID
ERCOT-25INR0717
Location
Bexar, Texas
Technology
Battery
Developer
Bexar Corrilla LLC
Market / region
ERCOT
Point of interconnection
TSP Station Name: Beck Road TSP Station Code: Z0 Load Name / Load Transformer Name: LXFMR3 Bus #: PTI Bus Number: 5035 Voltage (Transmission level kV): 138 Node (associated w/ load/load XFMR in NMMS): 0001

What stands out

1

Beck_Road BESS1 is a 10 MW Battery project in Texas with status active.

2

Bexar Corrilla LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-01-01.

Market and operating context

Queue date
2025-07-11
Proposed COD
2026-01-01
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Beck_Road BESS1 — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0717
LocationBexar, Texas
TechnologyBattery
DeveloperBexar Corrilla LLC
Market / regionERCOT
Point of interconnectionTSP Station Name: Beck Road TSP Station Code: Z0 Load Name / Load Transformer Name: LXFMR3 Bus #: PTI Bus Number: 5035 Voltage (Transmission level kV): 138 Node (associated w/ load/load XFMR in NMMS): 0001
Queue date2025-07-11
Proposed COD2026-01-01