Poteet BESS (ERCOT-25INR0715) — Project Summary

Queue ID
ERCOT-25INR0715
Capacity
9.95 MW
Technology
Battery
Status
active
Location
Atascosa, TX
Region
ERCOT
Developer
HEN INFRASTRUCTURE, LLC 1
IA Status
IA Executed

Poteet BESS

ERCOT-25INR0715BetaActiveBatteryERCOTLBNL

9.95 MW storage in Atascosa, TX · In queue since October 2024 · Proposed COD January 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

9.95 MW

Capacity

1

Components

Battery

1y 9m

In Queue

IA Executed

IA Phase

COD target: 2026

Interconnection

Total Duration

1y 3m

Schedule

5 months past proposed COD

Construction75%
Queue EntryOct 17, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-01-26

About

The Poteet BESS project is a proposed 9.95 MW battery storage project located in Atascosa County, Texas. Developed by HEN INFRASTRUCTURE, LLC 1, the project consists entirely of battery storage. It is interconnected within the ERCOT region under queue ID ERCOT-25INR0715, with an interconnection queue entry date of October 17, 2024, and a proposed commercial operation date of April 1, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)".

The proposed project is linked to the existing Poteet operating plant (EIA plant ID 67949). The point of interconnection is at the POTEET SUB station on the 69 kV bus. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Atascosa

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

HEN INFRASTRUCTURE, LLC 1

Utility

Entity

ERCOT

Service Type

Point of Interconnection

TSP Station Name: POTEET SUB TSP Station Code: POTEETS Load Name: POTEE_1 Bus#: 5710 kV: 69

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
POTEET_BESS
POI Substation
Poteet Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Poteet BESS
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.