Briefing/projectactive
Poteet BESS is a 10 MW Battery project in Texas, currently active.
HEN INFRASTRUCTURE, LLC 1 is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-01-26.
- Queue ID
- ERCOT-25INR0715
- Location
- Atascosa, Texas
- Technology
- Battery
- Developer
- HEN INFRASTRUCTURE, LLC 1
- Market / region
- ERCOT
- Point of interconnection
- TSP Station Name: POTEET SUB TSP Station Code: POTEETS Load Name: POTEE_1 Bus#: 5710 kV: 69
What stands out
1
Poteet BESS is a 10 MW Battery project in Texas with status active.
2
HEN INFRASTRUCTURE, LLC 1 is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-01-26.
Market and operating context
- Queue date
- 2024-10-17
- Proposed COD
- 2026-01-26
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.