Scenic Woods BESS
9.95 MW storage in Harris, TX · In queue since October 2024 · Proposed COD May 2025
9.95 MW
Capacity
1
Components
Battery
1y 7m
In Queue
In Progress (unknown study)
IA Status
Signed May 2024
IA → COD
1 year
Total Duration
1y 7m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-05-15
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Scenic Woods BESS project is a proposed 9.95 MW battery storage project located in Harris County, Texas. Developed by SMT Houston V LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0712. The project entered the interconnection queue on October 10, 2024, with a proposed commercial operation date of May 15, 2025.
The interconnection agreement for the Scenic Woods BESS project is currently listed as "In Progress (unknown study)" with an agreement date of May 7, 2024. The project has appeared in recent news coverage regarding energy storage developments in the ERCOT region.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SMT Houston V LLC
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Scenic Woods BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.