Compton BESS
9.95 MW storage in — · In queue since August 2024 · Proposed COD April 2027
9.95 MW
Capacity
1
Components
Battery
1y 11m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-08
The Compton BESS project is a proposed 9.95 MW battery storage project located in Dallas County, Texas. Developed by SMT Dallas VII LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0699. The project entered the interconnection queue on August 29, 2024, with a proposed commercial operation date of May 15, 2025.
The interconnection agreement for the Compton BESS project is currently listed as "In Progress (unknown study)". The point of interconnection is designated as POIB 2981 ERCOT Bus name COMPTON1_8 ERCOT load name LDLXFMR1 Oncor XFMR number 1. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SMT Dallas VII LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
POIB 2981 ERCOT Bus name COMPTON1_8 ERCOT load name LDLXFMR1 Oncor XFMR number 1
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Compton BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.