MESQUITE BESS
9.9 MW storage in Cameron, TX · Proposed COD February 2026
9.9 MW
Capacity
1
Components
Battery
—
In Queue
IA Executed
IA Phase
Signed Feb 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
IA → COD
2 years
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-02-16
Projected COD moved
4 times
Nov 2025 → Feb 2026
Net change
+3 months
first report to latest
Capacity
10 MW
unchanged in the reports
Latest stage
Commercial operation
last listed Feb 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Mesquite BESS is a proposed 9.9 MW battery energy storage development project in Cameron County, Texas. The project is being developed by Grenergy USA and is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under the identifier 25INR0697. It is a standalone storage project consisting of a single battery component rated at 9.9 MW.
The project's queue status is active. An interconnection agreement was executed on February 26, 2024, and the proposed commercial operation date is February 16, 2026. The designated point of interconnection is transformer 1 at the Mesquite substation, a 138 kV facility identified in ERCOT records under station code MESQUITE and bus number 8554. The project has been linked, with a match confidence of 0.92, to the Mesquite Clean Energy Center (BESS) in the U.S. Energy Information Administration's records (EIA plant ID 69457), associating the queue entry with an existing operating plant.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Feb 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Grenergy USA
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Substation: Mesquite, XFMR 1 Substation transmission kV: 138 ERCOT Station Long Name: MESQUITE ERCOT Station site code: MESQUITE ERCOT Bus#: 8554 ERCOT Load Name: Load1
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MESQUITE_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.