Slaton BESS
9.99 MW storage in — · In queue since June 2025 · Proposed COD August 2025
9.99 MW
Capacity
1
Components
Battery
11 months
In Queue
In Progress (unknown study)
IA Phase
COD target: 2025
Total Duration
2 months
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-31
No description available for this project.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Prairie Dog BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name: Slaton Substation • Station Code: LPLSL • BUS #: 59152 • Transmission Level Voltage: 115 kV • Load/Load Transformer: SLT1 • Node (associated w/ load/load XFMR in NMMS): SL15
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
No Ask reports yet for this entity.
Ask about Slaton BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.