Briefing/projectactive
Slaton BESS is a 10 MW Battery project in ERCOT, currently active.
Prairie Dog BESS, LLC is the reported developer. The reported queue phase is In Progress (unknown study). Proposed COD is 2025-08-31.
- Queue ID
- ERCOT-25INR0689
- Technology
- Battery
- Developer
- Prairie Dog BESS, LLC
- Market / region
- ERCOT
- Point of interconnection
- Station Name: Slaton Substation • Station Code: LPLSL • BUS #: 59152 • Transmission Level Voltage: 115 kV • Load/Load Transformer: SLT1 • Node (associated w/ load/load XFMR in NMMS): SL15
What stands out
1
Slaton BESS is a 10 MW Battery project with status active.
2
Prairie Dog BESS, LLC is the reported developer.
3
The reported queue phase is In Progress (unknown study); proposed COD is 2025-08-31.
Market and operating context
- Queue date
- 2025-06-12
- Proposed COD
- 2025-08-31
- IA status
- In Progress (unknown study)
- Study phase
- In Progress (unknown study)
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.