Giga Texas Data Center
133 MW storage in Travis, TX · In queue since August 2024 · Proposed COD December 2025
133 MW
Capacity
1
Components
Battery
1y 11m
In Queue
IA Executed
IA Phase
Signed Apr 2025
Queue → IA
8 months
IA → COD
8 months
Total Duration
8 months
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-12-15
The proposed Giga Texas Data Center project is a 133 MW battery storage development in Travis County, Texas. Developed by Giga Texas Energy, LLC, the project is located in the ERCOT region and entered the interconnection queue as ERCOT-25INR0688 on August 27, 2024. The proposed commercial operation date is December 15, 2025, and its interconnection status is currently in the Facility Study phase.
The project consists of 133 MW of battery storage. Interconnection will occur behind the meter at Medium Voltage 24.9 kV with non-export controls at the HORNSBY Substation. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Travis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Giga Texas Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
HORNSBY Substation POIB# 7047 Site will be connected behind the meter at Medium Voltage 24.9 kV with non export controls GSU TRANSFORMER 80/106/133MVA 345kV DELTA PRIMARY 24.9kV WYE-G SECONDARY Z=XX%, 65DEG C RISE
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Giga Texas Data CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.