Cuero BESS
9.99 MW storage in — · In queue since May 2024 · Proposed COD May 2026
9.99 MW
Capacity
1
Components
Battery
2y 6m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2 years
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-31
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cuero BESS is a proposed battery energy storage development project in the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by CUERO BESS, LLC and has a total planned capacity of 9.99 MW, consisting entirely of battery storage. According to its interconnection data, the project is associated with the CUERO LCRA station (station code CUERO, bus number 7244). That station operates at a transmission-level voltage of 138 kV and is linked to the Cuero T4 load transformer. The interconnection details also reference a 500 kVA, 12.47Y/7.2–0.48Y/0.277 kV, three-phase, liquid-filled outdoor transformer.
The project entered the ERCOT interconnection queue on May 22, 2024, under queue ID ERCOT-25INR0675, and its status is listed as active. Its interconnection agreement status is recorded as in progress, though the specific study phase is not identified. The proposed commercial operation date is May 31, 2026.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CUERO BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
500 kVA, 12.47Y/7.2-0.48Y/0.277kV, 3PH, 60Hz, Z=5.75%, Liquid Filled Type, Type 3R Outdoor_x000D_ • Station Name: CUERO LCRA_x000D_ • Station Code: CUERO_x000D_ • BUS #: 7244_x000D_ • Transmission Level Voltage: 138 kV_x000D_ • Load/Load Transformer: Cuero T4_x000D_
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.