Wooderson Energy Storage
306.4 MW storage in Jack, TX · In queue since May 2024 · Proposed COD September 2028
306.4 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Projected COD moved
3 times
Dec 2025 → Sep 2028
Net change
+33 months
first report to latest
Capacity
306 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-25inr0660-wooderson-energy-storage
- newsletter.interconnection.fyi/p/interconnectionfyi-weekly-digest
- groundtrace.io/projects/wooderson-energy-storage-2n4lbge3cbqhk
- bizapedia.com/tx/wooderson-energy-storage-llc.html
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0660/wooderson-energy-storage
Commercial operation date: Only the LBNL/ERCOT queue date of 2028-09-30 is available. Aggregator pages (infrasure, cleanview) repeat it, e.g. 'Proposed COD: 2028-09-30', so they are not independent confirmation. No developer press release or financing-backed target was found. The Dec 2024 digest's change from Sept 2027 to April 2028 is an older queue revision that the current queue date has since replaced.
Developer: Every source names Wooderson Energy Storage, LLC as the developer, and none identifies a parent or operating company. Bizapedia shows a Texas foreign-LLC registration (filed Jan 2026) with a North Carolina domestic jurisdiction, but no sponsor is named, so the LLC may be a shell for an unidentified developer.
Status: LBNL lists the project as active in Facility Study with no IA date. Recent aggregator pages (infrasure, 5 days ago) still show it as active, and no source reports withdrawal, construction or an executed IA.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Wooderson Energy Storage is a proposed 306.4 MW battery storage project located in Jack County, Texas. The project, developed by Wooderson Energy Storage, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0660, with a queue entry date of May 9, 2024. The proposed commercial operation date is September 30, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345 kV 11418 TECUMSEH- 1421 Willow Creek. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jack
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Wooderson Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 11418 TECUMSEH- 1421 Willow Creek
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Tecumseh Town Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Wooderson Energy Storage
Data-driven briefing on Wooderson Energy Storage — fleet, generation, financial, and news signals.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.