Carrizo Springs BESS
9.99 MW storage in Dimmit, TX · In queue since August 2024 · Proposed COD December 2025
9.99 MW
Capacity
1
Components
Battery
1y 11m
In Queue
IA Executed
IA Phase
COD target: 2025
Total Duration
1y 4m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-12-03
The Carrizo Springs BESS project is a proposed 9.99 MW battery storage project located in Dimmit County, Texas. The developer is Regis Carrizo Springs LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-25INR0592, with a queue entry date of August 22, 2024, and a proposed commercial operation date of May 30, 2025.
The project's Interconnection Agreement (IA) has been executed as of November 29, 2023. The point of interconnection (POI) is at the Carrizo Springs station on the 69 kV transmission line.
Generated from interconnection queue and public data sources
Realization history for this asset — final cost vs plan, COD slip vs original date, and construction duration vs cohort. Retrospective context for the operating risk view above. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Dimmit
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Regis Carrizo Springs LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name: CARRIZO SPRINGS Station Code: CARIZZO Load/Load XFMR Name: LOAD1 PTI Bus Number: #8244 Voltage in kV (Transmission): 69 kV Distribution Voltage: 12.47 kV
Data Source
LBNL
Composite operating risk view for this asset — climate hazards across its remaining operating life, observed generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — 10-year P50 trajectory accounting for degradation, observed curtailment, and market conditions, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this asset — 10-year cashflow projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Carrizo Springs BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.