Zeus Rusk BESS
208.8 MW generation in Rusk, TX · In queue since April 2024 · Proposed COD September 2027
208.8 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
Projected COD moved
1 time
Mar 2027 → Sep 2027
Net change
+6 months
first report to latest
Capacity
209 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Queue request submitted to ERCOT, Facility Study stage
cleanview.coResearch sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0591/zeus-rusk-bess
- ercotqueue.com/project/25INR0591
- interconnection.fyi/projects/state/TX
Commercial operation date: LBNL queue filing shows September 2027 COD. No independent news sources found to validate or contradict this date; only aggregator sites echoing the queue data.
Developer: LBNL filing entity is 'Rusk BESS, LLC', a project-specific LLC. No press releases, corporate announcements, or news coverage found to identify the parent operating company or developer.
Status: LBNL shows 'active' status in Facility Study phase. Ercotqueue.com claims 'Construction' status, but this appears to be a predictive model output rather than confirmed ground truth.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Zeus Rusk BESS (queue ID ERCOT-25INR0591) is a proposed battery energy storage development project in Rusk County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Rusk BESS, LLC and has a total proposed capacity of 208.8 MW. Although the queue record classifies the project's technology as Solar+Battery, its only listed component is a 208.8 MW battery system, and no solar capacity is specified. The project is categorized as a generation project, and its proposed point of interconnection is a tap on the 345 kV line between the Stryker and Martin Lake substations (Tap 345kV 3109 Stryker to 3100 Martin Lake).
The project entered the ERCOT interconnection queue on April 9, 2024, and its status is listed as active. It is currently in the Facility Study phase of the interconnection process, which means an interconnection agreement has not yet been reported. The proposed commercial operation date is September 1, 2027.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Rusk
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rusk BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3109 Stryker to 3100 Martin Lake
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Zeus Rusk BESS
Data-driven briefing on Zeus Rusk BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.