Albatross BESS 2 (ERCOT-25INR0579) — Project Summary

Queue ID
ERCOT-25INR0579
Capacity
159.6 MW
Technology
Battery
Status
active
Location
Mclennan, TX
Region
ERCOT
Developer
Albatross Solar, LLC
IA Status
Facility Study

Albatross BESS 2

ERCOT-25INR0579BetaActiveBatteryERCOTLBNL + Live

159.6 MW storage in Mclennan, TX · In queue since February 2024 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

159.6 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 10m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-30

Queue history
25INR0579 · 32 monthly ERCOT reports, Feb 2024 – Sep 2026

Projected COD moved

3 times

Jun 2025 → Dec 2028

Net change

+42 months

first report to latest

Capacity

108 → 160 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024
Facilities study approvedOct 30, 2025
Interconnection agreement signedSep 2, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Feb 22, 2028
Differs from queue: Dec 30, 2028From queue filing
Developer in saved assessment
Albatross Solar, LLC
From queue filing
Status at research time
Active
Active — in Facility Study phase, no IA executed, early-stage development with no construction timeline announced
Financing
Not recorded

Milestones in this assessment

IA executedFeb 27, 2024Latest in this assessment

Queue entry filed with ERCOT for 159.6 MW battery storage project in McLennan County

cleanview.co
Research sources and reasoning (7 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0579/albatross-bess-2
  2. interconnection.fyi/project/ercot-25inr0579
  3. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
  4. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
  5. infrastructureresearch.substack.com/p/the-battery-tell
  6. ercotqueue.com/developer/albatross-solar-llc
  7. ercotqueue.com/project/25INR0579

Commercial operation date: Only LBNL queue snapshot provides a COD target of 2028-02-22. No press releases, financing announcements, or developer statements found to validate or update this date. Project is still in Facility Study phase with no IA executed.

Developer: All sources consistently identify Albatross Solar, LLC as the developer. No parent company, operating entity, or ownership transfer information found in any search results. Entity appears to be the actual developer rather than a shell LLC.

Status: LBNL status 'active' confirmed by multiple queue-tracking sources (interconnection.fyi, ercotqueue.com). Project remains in pre-IA Facility Study phase with no public milestones beyond initial queue filing.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Albatross BESS 2 is a proposed 159.6 MW battery storage project located in McLennan County, Texas. The project, developed by Albatross Solar, LLC, is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-25INR0579 on February 27, 2024. Its proposed commercial operation date is February 22, 2028, and its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing Albatross Solar, LLC operating plant (EIA ID 66894). The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Mclennan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Albatross Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 165 Windsor Switch - 161 McGregor

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.