Stargazer Solar
157.7 MW hybrid in Brazoria, TX · In queue since October 2023 · Proposed COD February 2027
157.7 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-01
Projected COD moved
1 time
Dec 2025 → Feb 2027
Net change
+14 months
first report to latest
Capacity
158 MW
unchanged in the reports
Latest stage
Facilities study done
last listed Aug 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-25inr0555
- cleanview.co/planned-solar-projects/TX/25INR0555/stargazer-solar
- eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
- americas.rwe.com/our-energy/solar-energy/solar-projects-and-locations/stargazer-solar/
- protectmckeancountywilds.com/rwe-stargazer.html
Commercial operation date: LBNL queue snapshot proposes February 2027 COD. No independent news sources confirm or update this target for the Texas project; Cleanview aggregator echoes January 2027 but appears derivative of LBNL data.
Developer: LBNL filing entity is 'Stargazer Solar LLC', a project-specific shell. No press releases, corporate announcements, or news coverage identify the parent operating company or developer behind this Texas project. Note: RWE operates a separate 'Stargazer Solar' project in Pennsylvania (McKean County, 480 MW) with no evidence linking it to this ERCOT queue entry.
Status: LBNL status is 'active' with IA status at 'Facility Study'. No news coverage of this specific Texas project exists to contradict or enrich this baseline status.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Stargazer Solar is a proposed hybrid solar and battery storage development project in Brazoria County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Stargazer Solar LLC and has a total proposed capacity of 157.7 MW. The listed components specify 157.7 MW of solar generation. Battery storage is identified as part of the project's technology, but no separate battery capacity is provided. The project is planned to connect to the grid at the 44010 WA Parish – 42980 Nash 138 kV Circuit 02 transmission line.
The project entered the ERCOT interconnection queue on October 30, 2023, under queue ID ERCOT-25INR0555. Its proposed commercial operation date is February 1, 2027. The project's interconnection agreement status is listed as being in the Facility Study phase. Its overall queue status is currently recorded as suspended.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Aug 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Stargazer Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44010 WA Parish - 42980 Nash 138 kV Ckt 02
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.