Briefing/projectactive
Stargazer Solar is a 158 MW Solar+Battery project in Texas, currently active.
Stargazer Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-02-01.
- Queue ID
- ERCOT-25INR0555
- Location
- Brazoria, Texas
- Technology
- Solar+Battery
- Developer
- Stargazer Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- 44010 WA Parish - 42980 Nash 138 kV Ckt 02
What stands out
1
Stargazer Solar is a 158 MW Solar+Battery project in Texas with status active.
2
Stargazer Solar LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-02-01.
Market and operating context
- Queue date
- 2023-10-30
- Proposed COD
- 2027-02-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.