HarryoungBESS
190.01 MW generation in Cameron, TX · In queue since October 2023 · Proposed COD May 2028
190.01 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-15
Projected COD moved
2 times
Dec 2025 → May 2028
Net change
+29 months
first report to latest
Capacity
157 → 190 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion date updated from May 14, 2027 to May 14, 2028
interconnectionfyi.substack.comResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
- renewablesinfo.org/browse/owner/gransolar-group-grs
- ercotqueue.com/developer/gransolar-texas-four-llc
Commercial operation date: LBNL shows May 15, 2028. Interconnection.fyi newsletter (May 5, 2025) reports proposed completion changed from May 14, 2027 to May 14, 2028, confirming a recent update that pushed COD back ~1 year. Using May 14 date from the update.
Developer: LBNL filing entity is 'Gransolar Texas Four LLC' (project-specific shell). Multiple sources reference Gransolar Group (GRS) as the parent operating company with a portfolio of Texas projects including this one.
Status: LBNL shows 'active' status in Facility Study phase with no IA date. Recent queue update (April 2025) confirms project remains active with revised timeline.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The HarryoungBESS project is a proposed 190.01 MW battery storage project located in Cameron County, Texas. Developed by Gransolar Texas Four LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0552, with a queue entry date of October 4, 2023.
The proposed commercial operation date for HarryoungBESS is May 15, 2028. The project's interconnection status is currently in the Facility Study phase, and its point of interconnection is the 8319 Rio Hondo sub 138kV. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Four LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8319 Rio Hondo sub 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Rio Hondo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
HarryoungBESS
Data-driven briefing on HarryoungBESS — fleet, generation, financial, and news signals.
GRS Arbor Hills
Data-driven briefing on Gransolar Group (GRS) — fleet, generation, financial, and news signals.
GRS CMS
Data-driven briefing on Gransolar Group (GRS) — fleet, generation, financial, and news signals.
GRS C&C
Data-driven briefing on Gransolar Group (GRS) — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.