Monument Hill Solar
200 MW generation in Fayette, TX · In queue since October 2023 · Proposed COD June 2029
200 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
3y 6m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2029-06-30
Projected COD moved
2 times
Jun 2025 → Jun 2029
Net change
+48 months
first report to latest
Capacity
200 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement target date per ERCOT queue
interconnection.fyiResearch sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-25inr0512
- cleanview.co/power-projects/planned/solar-farms/texas/25INR0512/monument-hill-solar
- ercotqueue.com/project/25INR0512
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
Commercial operation date: Only LBNL queue data provides a COD target of June 2029. No news articles or press releases found discussing this specific project's timeline or construction schedule.
Developer: LBNL filing entity is 'RWE Solar Development, LLC' which is the project development subsidiary. Parent operating company is RWE, a major German utility with significant U.S. renewable operations.
Status: LBNL shows 'active' status with Facility Study in progress and IA date of December 2025. No contradictory information found in search results; project appears to be progressing through standard interconnection process.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Monument Hill Solar is a proposed 200 MW solar generation project located in Fayette County, Texas. The project, being developed by RWE Solar Development, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0512. It entered the interconnection queue on October 13, 2023, and has a proposed commercial operation date of June 30, 2029. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 200 MW of solar photovoltaic generation. Interconnection will occur at Tap 345kV 7055 Fayette - 9074 Lytton Springs. The project has been mentioned in recent news coverage related to the electric grid.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fayette
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 7055 Fayette - 9074 Lytton Springs
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FPPYD_FPP_G1
- POI Substation
- Fayette Plant #1 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.