Mud Cat Solar SLF
100.5 MW hybrid in Lamar, TX · In queue since October 2023 · Proposed COD September 2028
100.5 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-18
Mud Cat Solar SLF is a proposed solar generation project located in Lamar County, Texas. The project, developed by Mud Cat Solar, LLC, has a total capacity of 100.5 MW. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0505, with a queue entry date of October 20, 2023. The proposed commercial operation date is September 18, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Mud Cat Solar SLF is Tap 138KV 11768 Hawk Hollow _x0013_ 1768 Deport. The project consists of 100.5 MW of solar photovoltaic generation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mud Cat Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138KV 11768 Hawk Hollow – 1768 Deport
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Mud Cat Solar SLFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.