Longday Solar SLF
200.8 MW hybrid in Kinney, TX · In queue since July 2023 · Proposed COD December 2027
200.8 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
Projected COD moved
3 times
Jul 2026 → Dec 2027
Net change
+17 months
first report to latest
Capacity
201 → 201 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion date revised from March 2027 to December 2027
interconnection.fyiResearch sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-25inr0501
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
Commercial operation date: LBNL queue snapshot shows proposed COD of December 15, 2027. Interconnection.fyi newsletter (March 2025) notes the date was revised from March 14, 2027 to December 14, 2027, confirming the late-2027 timeframe. No contradictory developer announcements found.
Developer: LBNL filing entity is 'Longday Solar' with no evidence of a shell LLC structure. No press releases, corporate announcements, or ownership changes found in search results. Developer name appears consistent across all sources.
Status: LBNL shows 'active' status in Facility Study phase (queue date July 2023). No news of construction start, financing, or status changes found in search results.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Longday Solar SLF project is a proposed 200.8 MW solar generation facility located in Kinney County, Texas. The project, developed by Longday Solar, is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0501, with a queue entry date of July 31, 2023. The proposed commercial operation date is December 15, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap138 kV 8252 Brackettville - 8260 Escondido. The Longday Solar SLF project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Longday Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap138 kV 8252 Brackettville - 8260 Escondido
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ECLIPSE_UN1
- POI Substation
- Brackettville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.