Dolomite Storage
125.7 MW storage in Ellis, TX · In queue since September 2023 · Proposed COD December 2026
125.7 MW
Capacity
1
Components
Battery
3y 2m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
Projected COD moved
0 times
Dec 2026 → Dec 2026
Net change
0 months
first report to latest
Capacity
126 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Expected online date July 2028 per EIA tracking
cleanview.coResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/68166_DOLBA/dolomite-storage
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
- ercotqueue.com/developer/bt-wilson-storage-llc
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: LBNL queue shows December 2026 COD, but Cleanview (aggregator tracking EIA data) reports July 2028 expected online date in multiple listings. The 1.5-year slip is consistent with typical battery storage project delays during facility study phase.
Developer: LBNL filing entity is 'BT Wilson Storage, LLC' (project-specific shell). EIA data identifies the parent as 'Belltown Power Texas 2, LLC' / 'Belltown Power', the actual operating company behind multiple Texas battery projects.
Status: LBNL status is 'active' with IA status 'Facility Study'. No press releases or construction announcements found; project remains in pre-construction interconnection study phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Dolomite Storage project is a proposed 125.7 MW battery energy storage system in Ellis County, Texas. Developed by BT Wilson Storage, LLC, the project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-25INR0495 on September 8, 2023. The proposed commercial operation date is December 1, 2026, and the project is currently in the Facility Study phase of the interconnection process.
The proposed project is linked to the existing Dolomite Storage operating plant (EIA ID 68166). The interconnection point of contact is the 218 Rockett 69kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Wilson Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
218 Rockett 69kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.