Blue Summit Energy Storage
100 MW generation in Wilbarger, TX · In queue since October 2023 · Proposed COD July 2026
100 MW
Capacity
1
Components
Battery
3y 1m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 24–36 months
Proposed COD: 2026-07-31
Projected COD moved
4 times
Jul 2026 → Jul 2026
Net change
0 months
first report to latest
Capacity
75 → 100 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
ERCOT capacity tracking lists March 2026 expected online date
ercot.comResearch sources and reasoning (4 recorded sources)
high confidence at research time
- nexteraenergyresources.com/pdf/NEER-2020-Energy-Storage.pdf
- renewablesinfo.org/project/ercot-25inr0492-blue-summit-energy-storage
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
- ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
Commercial operation date: LBNL proposed COD is 2026-04-03. ERCOT capacity tracking documents (March 2025 and PUC Texas generator table) both list 'Mar-26' as the expected online date, confirming a Q1 2026 target consistent with LBNL but slightly earlier in the month.
Developer: LBNL filing entity is 'NextEra Energy Interconnection Holdings, LLC' (a project-holding subsidiary). NextEra's 2020 energy storage business presentation explicitly lists 'Blue Summit Energy Storage' as part of NextEra Energy Resources' portfolio, confirming the parent operating company.
Status: LBNL status is 'active' with IA Executed. ERCOT's February 2025 capacity change tracking and PUC Texas generator table both list the project as expected online March 2026, confirming active development status.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Blue Summit Energy Storage is a proposed 100 MW battery storage project in Wilbarger County, Texas. The project, developed by NextEra Energy Interconnection Holdings, LLC, is located within the ERCOT region and entered the ERCOT interconnection queue as ERCOT-25INR0492 on October 20, 2023. The proposed commercial operation date is April 3, 2026.
The project's interconnection agreement has been executed, with an agreement date of February 22, 2012. The point of interconnection is the 61001 JIM TREECE 345kV. The project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
61001 JIM TREECE 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Jim Treece Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesBlue Summit Energy Storage
Data-driven briefing on Blue Summit Energy Storage — fleet, generation, financial, and news signals.
A specific company (e.g., NextEra Energy, Duke Energy)
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra Energy
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
NextEra entity test
Data-driven briefing on NextEra Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.