Acker BESS (ERCOT-25INR0460) — Project Summary

Queue ID
ERCOT-25INR0460
Capacity
301.04 MW
Technology
Battery
Status
active
Location
Castro, TX
Region
ERCOT
Developer
Ogallala BESS LLC
IA Status
IA Executed

Acker BESS

ERCOT-25INR0460BetaActiveBatteryERCOTLBNL + Live

301.04 MW storage in Castro, TX · In queue since June 2023 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

301.04 MW

Capacity

1

Components

Battery

3y 5m

In Queue

IA Executed

IA Phase

Signed Apr 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 10m

IA → COD

4 years

Total Duration

1y 10m

Construction75%
Queue EntryJun 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementApr 21, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2029-04-17

Queue history
25INR0460 · 41 monthly ERCOT reports, May 2023 – Sep 2026

Projected COD moved

4 times

Dec 2025 → Apr 2029

Net change

+40 months

first report to latest

Capacity

301 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 7, 2023
Facilities study approvedFeb 4, 2025
Interconnection agreement signedApr 21, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 17, 2029
From queue filing
Developer in saved assessment
Ogallala BESS LLC
From queue filing
Status at research time
IA Executed
Active in the ERCOT queue with a Standard Generation Interconnection Agreement with Oncor executed April 2025 and filed at the Texas PUC in May 2025. No construction or financing announcements found.
Financing
Not recorded

Milestones in this assessment

IA executedApr 21, 2025Latest in this assessment

Interconnection agreement date added for the 301MW Acker BESS in Castro, TX. The newsletter says April 20, 2025 and LBNL says 2025-04-21; the Oncor agreement was later filed at the Texas PUC on 5/15/2025.

newsletter.interconnection.fyi
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. newsletter.interconnection.fyi/p/interconnection-weekly-project-updates-db7
  2. interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&DocumentType=ALL&SortBy=FilingParty&SortOrder=Ascending
  3. cleanview.co/planned-battery-projects/TX/25INR0460/acker-bess
  4. ercotqueue.com/project/25INR0460
  5. infrasure.ai/project/ercot-25inr0460-acker-bess

Commercial operation date: LBNL lists 2029-04-17. Only one aggregator, Cleanview, says the project is 'expected to come online in April 2028'. That is a single, non-developer signal, so it does not meet the 2+ source bar to override LBNL. The ~1-year gap is flagged as a minor disagreement.

Developer: Ogallala BESS LLC appears as developer in LBNL, ercotqueue.com and infrasure.ai, with no parent or operating company named anywhere. The Oncor interconnection agreement at the Texas PUC names 'Acker BESS LLC' as the project entity, which looks like a project-level SPV. No sponsor or ownership change is documented.

Status: LBNL shows status active with IA Executed (2025-04-21). The PUC docket (Oncor and Acker BESS LLC, filed 5/15/2025) and the interconnection.fyi newsletter (IA date added April 2025) corroborate the IA. No evidence of withdrawal or suspension.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Acker BESS project is a proposed 301.04 MW battery storage project located in Castro County, Texas. Developed by Ogallala BESS LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0460, with a queue entry date of June 7, 2023.

The proposed commercial operation date for the Acker BESS project is April 17, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the 23912 Ogallala 345 kV substation.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Castro

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Ogallala BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

23912 Ogallala 345 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Ogallala Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.