Marengo BESS
120.72 MW storage in Cameron, TX · In queue since May 2023 · Proposed COD May 2028
120.72 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-15
Projected COD moved
1 time
Sep 2025 → May 2028
Net change
+32 months
first report to latest
Capacity
121 MW
unchanged in the reports
Latest stage
Cancelled
last listed Apr 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- renewablesinfo.org/project/ercot-25inr0419-marengo-bess
- interconnection.fyi/project/ercot-25inr0419
- ercotqueue.com/project/25INR0419
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: Only LBNL queue data provides a COD estimate (2028-05-15). No news or research findings mention construction timeline, financing, or updated COD targets for this Texas project.
Developer: All sources consistently identify 'BRP BLUE TOPAZ 8, LLC' as the developer. No parent company or operating entity is mentioned in any search results. BRP appears to be the actual developer entity, not a shell LLC.
Status: LBNL shows 'Active' status in Facility Study phase. No news coverage exists for this specific Texas project; search results primarily returned an unrelated Illinois project with the same 'Marengo BESS' name.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Marengo BESS project is a proposed 120.72 MW battery storage project located in Cameron County, Texas. The developer is BRP BLUE TOPAZ 8, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0419, with a queue entry date of May 15, 2023, and a proposed commercial operation date of May 15, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the Marengo BESS project is the 8640 Kelvin Station 138kV (AEP). The project has appeared in recent news coverage regarding energy storage developments in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Apr 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP BLUE TOPAZ 8, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8640 Kelvin Station 138kV (AEP)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.