Briefing on Marengo BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
121 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-05-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Marengo BESS is a 121 MW Battery project in Texas, currently active.

BRP BLUE TOPAZ 8, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-05-15.

Queue ID
ERCOT-25INR0419
Location
Cameron, Texas
Technology
Battery
Developer
BRP BLUE TOPAZ 8, LLC
Market / region
ERCOT
Point of interconnection
8640 Kelvin Station 138kV (AEP)

What stands out

1

Marengo BESS is a 121 MW Battery project in Texas with status active.

2

BRP BLUE TOPAZ 8, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-05-15.

Market and operating context

Queue date
2023-05-15
Proposed COD
2028-05-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Marengo BESS — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0419
LocationCameron, Texas
TechnologyBattery
DeveloperBRP BLUE TOPAZ 8, LLC
Market / regionERCOT
Point of interconnection8640 Kelvin Station 138kV (AEP)
Queue date2023-05-15
Proposed COD2028-05-15