Rogers Creek BESS
100.33 MW storage in Cherokee, TX · In queue since May 2023 · Proposed COD April 2028
100.33 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-19
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Rogers Creek BESS project is a proposed 100.33 MW battery storage project located in Cherokee County, Texas. Developed by Dialville BESS, the project entered the ERCOT interconnection queue as entry ERCOT-25INR0414 on May 15, 2023. The current proposed commercial operation date is April 19, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of a single 100.33 MW battery component. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Cherokee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dialville BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV DailVille (3160) - Neches Pump (3296)
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Rogers Creek BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.