Diaz BESS
241.48 MW storage in Cameron, TX · In queue since May 2023 · Proposed COD November 2027
241.48 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-18
Projected COD moved
1 time
Sep 2025 → Nov 2027
Net change
+26 months
first report to latest
Capacity
244 → 241 MW
changed in the reports
Latest stage
Cancelled
last listed Feb 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion changed from August 31, 2025 to November 17, 2027
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- interconnection.fyi/project/ercot-25inr0386
- interconnection.fyi/projects/state/TX/cameron-county
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- infrasure.ai/project/ercot-25inr0386-diaz-bess
- renewablesinfo.org/project/ercot-25inr0386-diaz-bess
Commercial operation date: LBNL proposes 2027-11-18 COD. Interconnection.fyi notes the proposed completion changed from August 2025 to November 2027, confirming the LBNL date is the current target. No independent developer announcements found to validate or contradict.
Developer: Only LBNL filing entity 'BRP Blue Topaz 10, LLC' is documented across all sources. No press releases or corporate announcements found identifying a parent operating company. BRP entities are typically project SPVs but no parent identified in available sources.
Status: Interconnection.fyi explicitly states 'The project is currently withdrawn in the ERCOT' and Cameron County queue listing shows status as 'Withdrawn'. LBNL snapshot is stale.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Diaz BESS project is a proposed 241.48 MW battery storage project located in Cameron County, Texas. Developed by BRP Blue Topaz 10, LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0386, with a queue entry date of May 22, 2023.
The proposed commercial operation date (COD) for the Diaz BESS project is November 18, 2027. Its interconnection status is currently in the Facility Study phase, and its point of interconnection (POI) is the 8950 Olmito 138kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Feb 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Blue Topaz 10, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8950 Olmito 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OLMITO_RN
- POI Substation
- Olmito Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Diaz BESS
Data-driven briefing on Diaz BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.