Hawkins BESS
150.43 MW storage in Hidalgo, TX · In queue since May 2023 · Proposed COD January 2028
150.43 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-16
Projected COD moved
1 time
Sep 2025 → Jan 2028
Net change
+28 months
first report to latest
Capacity
150 → 150 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Research sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0376/hawkins-bess
- interconnection.fyi/project/ercot-25inr0376
- ercotqueue.com/project/25INR0376
Commercial operation date: Only LBNL queue data provides a COD target of January 2028. No press releases, financing announcements, or developer statements found to validate or update this date.
Developer: LBNL filing entity is 'BRP BLUE TOPAZ 7, LLC' which appears to be a project-LLC shell. No press releases, corporate announcements, or news coverage identify the parent operating company. Search results only echo LBNL data.
Status: LBNL status is 'active' at Facility Study stage. No news coverage or developer announcements found to indicate construction progress, financing, or permitting milestones beyond queue position.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Hawkins BESS is a proposed 150.43 MW battery storage project located in Hidalgo County, Texas. The project, developed by BRP BLUE TOPAZ 7, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0376. The project consists of a single 150.43 MW battery component.
The project entered the ERCOT interconnection queue on May 3, 2023, with a proposed commercial operation date of January 16, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the 85005 ELGATO4A 138 kV location.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP BLUE TOPAZ 7, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
85005 ELGATO4A 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.