Briefing on Hawkins BESS

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
150 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-01-16
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Hawkins BESS is a 150 MW Battery project in Texas, currently active.

BRP BLUE TOPAZ 7, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-01-16.

Queue ID
ERCOT-25INR0376
Location
Hidalgo, Texas
Technology
Battery
Developer
BRP BLUE TOPAZ 7, LLC
Market / region
ERCOT
Point of interconnection
85005 ELGATO4A 138 kV

What stands out

1

Hawkins BESS is a 150 MW Battery project in Texas with status active.

2

BRP BLUE TOPAZ 7, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-01-16.

Market and operating context

Queue date
2023-05-03
Proposed COD
2028-01-16
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Hawkins BESS — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0376
LocationHidalgo, Texas
TechnologyBattery
DeveloperBRP BLUE TOPAZ 7, LLC
Market / regionERCOT
Point of interconnection85005 ELGATO4A 138 kV
Queue date2023-05-03
Proposed COD2028-01-16