IEP Blackhawk (ERCOT-25INR0310) — Project Summary

Queue ID
ERCOT-25INR0310
Capacity
100 MW
Technology
Battery
Status
active
Location
Galveston, TX
Region
ERCOT
Developer
IEP Texas Verde II, llc
IA Status
Facility Study

IEP Blackhawk

ERCOT-25INR0310BetaActiveBatteryERCOTLBNL + Live

100 MW storage in Galveston, TX · In queue since April 2023 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

100 MW

Capacity

1

Components

Battery

3y 7m

In Queue

Facility Study

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 8m

Facilities Study50%
Queue EntryApr 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Queue history
25INR0310 · 43 monthly ERCOT reports, Mar 2023 – Sep 2026

Projected COD moved

1 time

Jan 2025 → Dec 2026

Net change

+23 months

first report to latest

Capacity

100 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 7, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Nov 2026
Differs from queue: Dec 1, 2026
Developer in saved assessment
Intersect Power
Filed as IEP Texas Verde II, llc
Status at research time
Active
Active — Facility Study stage, no IA executed yet. Project appears on track for 2026 COD based on multiple 2025-2026 references.
Financing
Not recorded

Milestones in this assessment

COD targetNov 2026Latest in this assessment

500MWh project targeted for November 2026 commercial operation

fuzzypandaresearch.com
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0310/iep-blackhawk
  2. interconnection.fyi/projects/state/TX/galveston-county
  3. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
  4. txnmenergy.com/~/media/Files/P/PNM-Resources/rates-and-filings/FERC/2024%20TNMP%20FERC%20Form%201.pdf
  5. fuzzypandaresearch.com/eos-energy-eose-deadly-gas-doe-loan-default/
  6. x.com/bert_gilfoyle/status/2054963083471454427

Commercial operation date: LBNL shows 2026-12-01, but Fuzzy Panda Research (Oct 2025) states '500MWh supposed to come online in November 2026' and Twitter source (May 2026) mentions 'early as 2026 COD'. Consensus is November 2026, one month earlier than LBNL.

Developer: LBNL filing entity is 'IEP Texas Verde II, llc' which is a project LLC. IEP prefix indicates Intersect Power (formerly Intersect Energy Partners), a major utility-scale solar and storage developer. The LLC is a shell entity for this specific project.

Status: LBNL status is 'active' at Facility Study stage. Multiple recent sources (Oct 2025, May 2026) reference the project as ongoing with 2026 target, confirming active development status.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The IEP Blackhawk project is a proposed 100 MW battery storage project located in Galveston County, Texas. Developed by IEP Texas Verde II, llc, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0310, with a queue entry date of April 7, 2023. The proposed commercial operation date is December 1, 2026.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 38740 Heights Substation 138kV. The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Galveston

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

IEP Texas Verde II, llc

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

38740 Heights Substation 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Central Heights Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.