Hide Town Energy Storage (ERCOT-25INR0287) — Project Summary

Queue ID
ERCOT-25INR0287
Capacity
100.75 MW
Technology
Battery
Status
active
Location
Scurry, TX
Region
ERCOT
Developer
Hide Town Energy Storage LLC
IA Status
Facility Study

Hide Town Energy Storage

ERCOT-25INR0287BetaActiveBatteryERCOTLBNL + Live

100.75 MW storage in Scurry, TX · In queue since January 2023 · Proposed COD October 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

100.75 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 9m

Facilities Study50%
Queue EntryJan 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-11

Queue history
25INR0287 · 18 monthly ERCOT reports, Apr 2025 – Sep 2026

Projected COD moved

2 times

May 2028 → Oct 2029

Net change

+17 months

first report to latest

Capacity

101 → 103 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 17, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2029
From queue filing
Developer in saved assessment
Doral Renewables LLC
Filed as Hide Town Energy Storage LLC
Status at research time
Active
Active — Facility Study phase in ERCOT queue, early-stage development with no construction timeline announced
Financing
Not recorded

Milestones in this assessment

COD targetOct 2029Latest in this assessment

Proposed commercial operation date per ERCOT queue filing

cleanview.co
Research sources and reasoning (3 recorded sources)

medium confidence at research time

  1. doral-llc.com/projects/hide-town-energy-storage/
  2. doral-llc.com/solution/battery-storage/
  3. cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0287/hide-town-energy-storage

Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-10-11. Cleanview aggregator confirms 'Expected online 2029'. No contradictory news sources found.

Developer: LBNL filing entity is 'Hide Town Energy Storage LLC' (project-specific shell). Doral LLC's website explicitly lists Hide Town Energy Storage as their project, and their battery storage page describes their development capabilities. Doral Renewables LLC is the operating parent company.

Status: LBNL shows 'active' status in Facility Study phase (no IA executed yet). Doral website confirms project exists in their portfolio but provides no construction or financing updates. No withdrawal or suspension signals found.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Hide Town Energy Storage is a proposed battery energy storage development project located in Scurry County, Texas. The project is being developed by Hide Town Energy Storage LLC and has a total planned capacity of 100.75 MW, consisting entirely of battery storage. It is designed to connect to the grid at the 1311 SACROC 138kV point of interconnection.

The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under the identifier ERCOT-25INR0287. It entered the queue on January 17, 2023, and its status remains active. The project is currently in the Facility Study phase of the interconnection process. Its proposed commercial operation date is October 11, 2029.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Scurry

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Hide Town Energy Storage LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

1311 SACROC 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Sacroc Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.