Hide Town Energy Storage
100.75 MW storage in Scurry, TX · In queue since January 2023 · Proposed COD October 2029
100.75 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-11
Projected COD moved
2 times
May 2028 → Oct 2029
Net change
+17 months
first report to latest
Capacity
101 → 103 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per ERCOT queue filing
cleanview.coResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- doral-llc.com/projects/hide-town-energy-storage/
- doral-llc.com/solution/battery-storage/
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0287/hide-town-energy-storage
Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-10-11. Cleanview aggregator confirms 'Expected online 2029'. No contradictory news sources found.
Developer: LBNL filing entity is 'Hide Town Energy Storage LLC' (project-specific shell). Doral LLC's website explicitly lists Hide Town Energy Storage as their project, and their battery storage page describes their development capabilities. Doral Renewables LLC is the operating parent company.
Status: LBNL shows 'active' status in Facility Study phase (no IA executed yet). Doral website confirms project exists in their portfolio but provides no construction or financing updates. No withdrawal or suspension signals found.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Hide Town Energy Storage is a proposed battery energy storage development project located in Scurry County, Texas. The project is being developed by Hide Town Energy Storage LLC and has a total planned capacity of 100.75 MW, consisting entirely of battery storage. It is designed to connect to the grid at the 1311 SACROC 138kV point of interconnection.
The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under the identifier ERCOT-25INR0287. It entered the queue on January 17, 2023, and its status remains active. The project is currently in the Facility Study phase of the interconnection process. Its proposed commercial operation date is October 11, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hide Town Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1311 SACROC 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Sacroc Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.