City Breeze BESS
143.1 MW storage in Matagorda, TX · In queue since December 2022 · Proposed COD March 2027
143.1 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Phase
Signed May 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 5m
IA → COD
2y 10m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-03-18
Projected COD moved
4 times
Dec 2025 → Mar 2027
Net change
+15 months
first report to latest
Capacity
101 → 143 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Original IA executed with AEP Texas, later amended/restated October 2024
interchange.puc.texas.govERCOT interconnection study lists updated COD target
ercot.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- baycitytribune.com/news/235-megawatt-battery-storage-facility-in-matagorda-county-moves-forward/article_03739a84-d462-44f8-9de7-d77bddcd58f4.html
- ercot.com/files/docs/2025/02/21/EIR%20-%20CNP%20-%20Southwest%20Houston%20345-kV%20Reliability%20Project_February_RPG.pdf
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/09/26/ERCOT_BESS_Buildout_Report_August_2024.xlsx
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1953
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
Commercial operation date: LBNL queue shows 2027-03-18, but ERCOT's February 2025 Southwest Houston 345-kV Reliability Project document lists City Breeze BESS with COD 07/15/2026 (140.6 MW). This is an 8-month earlier target, reflecting updated interconnection study timelines.
Developer: LBNL filing entity is 'City Breeze BESS LLC' (project shell). Modo Energy's August 2024 ERCOT BESS Buildout Report explicitly lists 'Zenobe City Breeze BESS' as the developer name, indicating Zenobe Energy is the parent/operating company.
Status: LBNL status 'Active' with IA executed 2024-05-15 is confirmed. Texas PUC filing 35077-1953 shows First Amended & Restated ERCOT Standard Generation Interconnection Agreement filed October 2024, indicating active progression.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The City Breeze BESS project is a proposed 140.6 MW battery storage project located in Matagorda County, Texas. The project, developed by City Breeze BESS LLC, interconnected to the ERCOT grid at the 8111 MAGILL4A 138KV point of interconnection. It entered the ERCOT interconnection queue as queue ID ERCOT-25INR0271 on December 15, 2022, and has a proposed commercial operation date of March 18, 2027.
The project's Interconnection Agreement (IA) was executed on May 15, 2024. The project has appeared in recent news coverage regarding energy storage development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
City Breeze BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8111 MAGILL4A 138KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.