Briefing/projectactive
City Breeze BESS is a 143 MW Battery project in Texas, currently active.
City Breeze BESS LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-03-18.
- Queue ID
- ERCOT-25INR0271
- Location
- Matagorda, Texas
- Technology
- Battery
- Developer
- City Breeze BESS LLC
- Market / region
- ERCOT
- Point of interconnection
- 8111 MAGILL4A 138KV
What stands out
1
City Breeze BESS is a 143 MW Battery project in Texas with status active.
2
City Breeze BESS LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-03-18.
Market and operating context
- Queue date
- 2022-12-15
- Proposed COD
- 2027-03-18
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.