Whiskey BESS (ERCOT-25INR0253) — Project Summary

Queue ID
ERCOT-25INR0253
Capacity
153.72 MW
Technology
Battery
Status
active
Location
Van Zandt, TX
Region
ERCOT
Developer
Whiskey BESS LLC
IA Status
IA Executed

Whiskey BESS

ERCOT-25INR0253BetaActiveBatteryERCOTLBNL + Live

153.72 MW storage in Van Zandt, TX · In queue since December 2022 · Proposed COD July 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

153.72 MW

Capacity

1

Components

Battery

3y 11m

In Queue

IA Executed

IA Phase

Signed Mar 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 3m

IA → COD

2y 4m

Total Duration

2y 3m

Construction75%
Queue EntryDec 7, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 28, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-07-31

Queue history
25INR0253 · 41 monthly ERCOT reports, May 2023 – Sep 2026

Projected COD moved

3 times

Jul 2025 → Jul 2027

Net change

+24 months

first report to latest

Capacity

150 → 154 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 7, 2022
Facilities study approvedJun 3, 2024
Interconnection agreement signedMar 28, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jul 2027
From queue filing
Developer in saved assessment
—
From queue filing
Status at research time
IA Executed
IA Executed — IA signed 2025-03-28 per LBNL, construction estimated to start Jan 2026 per local opposition group
Financing
Not recorded

Milestones in this assessment

IA executedMar 28, 2025

Interconnection Agreement executed between Rayburn and Whiskey BESS LLC, filed at Texas PUC

interchange.puc.texas.gov
COD targetJul 2027Latest in this assessment

Texas PUC gentable lists Whiskey BESS 154 MW with Jan-27 expected online date

ftp.puc.texas.gov
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0253/whiskey-bess
  2. savevzcounty.org/current-projects
  3. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
  4. ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025_PlannedMonthly.xlsx
  5. interchange.puc.texas.gov/Documents/35077_2099_1484476.PDF
  6. ercotqueue.com/project/25INR0253

Commercial operation date: LBNL queue shows 2027-07-31 COD with IA executed 2025-03-28. Texas PUC gentable.xls (Jan 2026) confirms 'Jan-27' target. Facebook post claims 'In production March 2026' but lacks credibility vs official filings. No developer press releases found to contradict LBNL date.

Developer: Only entity identified is 'Whiskey BESS LLC' from LBNL filing and ERCOT documents. No parent company, operating entity, or developer press releases found in search results. This appears to be a project-specific LLC with no public disclosure of backing entity.

Status: LBNL shows 'IA Executed' status with 2025-03-28 IA date. Save Van Zandt County website (local opposition group) indicates 'Est Build Start: Jan 2026'. No evidence of construction commencement or withdrawal.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Whiskey BESS project is a proposed 153.72 MW battery storage project located in Van Zandt County, Texas. Developed by UR-Silo DevCo LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0253, with a queue entry date of December 7, 2022.

The proposed commercial operation date for Whiskey BESS is July 31, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 6828 Canton Tap 138 kV. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Van Zandt

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Whiskey BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

6828 Canton Tap 138 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.